Energy-Saving Dryer Replacement and Pipework Modification for Food Manufacturer in Kent

We are committed to providing comprehensive solutions for various industries. This case study showcases our recent accomplishment in the food manufacturing sector, where we successfully replaced a faulty MTA dryer with an Atlas Copco FX19.5 unit. Additionally, we executed precise modifications to the existing pipework, ensuring seamless integration with the new dryer. Our skilled fitters demonstrated their expertise and dedication, delivering outstanding results for our valued client.

Project Overview:
Over the weekend, our team focused on addressing the specific needs of a food manufacturer in Kent. The primary objective was to remove the faulty MTA dryer and replace it with an efficient Atlas Copco FX19.5 unit. The project also involved modifying the existing 5″ and 4″ pipework and introducing 110mm pipework to accommodate the new dryer. To ensure a smooth transition, the site electrician was scheduled to build a frame for the isolator on the following Monday.

Challenges Faced:
1. Limited Downtime: As the food manufacturing industry operates on strict schedules, minimizing production downtime was critical. Our team had to execute the installation swiftly and efficiently to avoid disrupting the client’s operations.

2. Precision Modifications: The existing pipework required modifications to accommodate the new dryer effectively. Ensuring precise adjustments and seamless integration was crucial to maintain the integrity and efficiency of the entire system.

Execution and Results:
Our experienced fitters successfully executed the project, delivering exceptional results within the specified timeframe. Key steps included:

1. Faulty Dryer Removal: Our team efficiently removed the faulty MTA dryer, ensuring minimal disruption to the client’s operations. Careful planning and coordination were crucial to maintain production continuity.

2. Atlas Copco FX19.5 Installation: We seamlessly installed the new Atlas Copco FX19.5 dryer, leveraging our expertise in handling advanced equipment. The installation was carried out with precision, ensuring optimal performance and energy efficiency.

3. Pipework Modifications: Our skilled fitters executed the necessary modifications to the existing 5″ and 4″ pipework, as well as the introduction of 110mm pipework. This meticulous adjustment allowed for seamless integration with the new dryer, optimizing airflow and preventing any potential bottlenecks.

4. Collaboration with Site Electrician: To complete the project, our team collaborated with the site electrician, who will be constructing a frame for the isolator. This ensured the necessary electrical safety measures were in place before the dryer’s operation.

Conclusion:
Our team’s efficient execution and dedication played a crucial role in the successful replacement of the faulty MTA dryer with the efficient Atlas Copco FX19.5 unit for our food manufacturing client in Kent. The precise modifications made to the pipework ensured seamless integration, optimizing airflow and preventing any potential disruptions. By minimizing downtime and collaborating effectively with the site electrician, we provided our client with a reliable and efficient solution. Our fitters’ outstanding efforts and commitment to excellence once again showcased our ability to deliver exceptional results and meet the unique requirements of our valued clients in the food manufacturing industry.

Back to Case Studies

More case studies

20230621_132925-scaled-1

Efficient Installation of Air Compressors and Ringmain for a Prominent Pharmaceutical Company

At AMS Compressor Services, we pride ourselves on delivering exceptional turnkey solutions

Read More
20220520_133249-scaled

Swift Installation of Pipe Ring Main for Global Instrumentation Company

At AMS, we thrive on taking up new and exciting projects every

Read More
20221127_155240-scaled

Successful Relocation of Compressed Air System for Petroleum Testing Facility

We are thrilled to announce another successful project completion, as our dedicated

Read More

Trusted by